CARNO WIND FARM – PHASE I
CARNO PHASE I
Built in 1996 the Carno I site comprises 56 wind turbines, each rated at 600kW giving a total installed capacity of 33.6MW. The site generates 63,300MWh of electricity per annum, enough to meet the domestic needs of 18,039 homes*.
The site is owned and operated by Ventient Energy and at the time of its construction, it was the largest onshore wind farm in Europe.
*Based on an average energy yield and assumed annual household usage of 3.509 kWh per year. Typical Domestic Consumption Values from BEIS Subnational electricity and gas consumption summary report 2021 (publishing.service.gov.uk)
CARNO I – SITE DETAILS
Installed Capacity
33.6MW
Number of Turbines
56
Turbine Type
Bonus 600kW
Hub height
31.5m
Blade length
19.1m
Annual Energy Generated
63,300 MWh
Annual house-hold power equivalent
18,039 homes*